Monday, 27 February 2017
Wednesday, 15 February 2017
Yard cleared
The backyard excavated and cleared of concrete left behind during demolition. Looks so much cleaner now.
Friday, 3 February 2017
Wednesday, 1 February 2017
Slab has been laid…
The Truck parade started in the morning. .....
More than 10 concrete trucks drove in and out of the site all day. Concrete pump tirelessly completed the slap pouring in 5 hours. Finally we were able to walk on the floors. The slab was perfectly laid with the exact shapes as drawn in the plan. Witnessing the physical layout is always pleasing for your eyes and feet. Waiting time starts now until we have the slap stable enough to take the frames up. After years of waiting and months of preparation and anticipation, we have the house foundation ready.
More than 10 concrete trucks drove in and out of the site all day. Concrete pump tirelessly completed the slap pouring in 5 hours. Finally we were able to walk on the floors. The slab was perfectly laid with the exact shapes as drawn in the plan. Witnessing the physical layout is always pleasing for your eyes and feet. Waiting time starts now until we have the slap stable enough to take the frames up. After years of waiting and months of preparation and anticipation, we have the house foundation ready.
Monday, 30 January 2017
Ready to Pour
Prep work for slab continued today and concrete will be poured on Wednesday - Hoping for no rain to pour on that day.
Pre-Inspection to take place tomorrow.
Friday, 27 January 2017
Getting ready for the Slab
Wednesday, 25 January 2017
Get Set, Ready .........
The contractors shipped in waffle pods and a tonne of wire mesh. Seeing the materials delivered to our site fulfils your day.
Subscribe to:
Posts (Atom)