Frames - 2nd Day
Rest of the frames came very early in the morning today. The ground floor is half finished.
No more work till the steel comes in next week :-(
Entrance
Monday, 27 March 2017
Frames are up - 1st Day
Finally we can see something raising out of the ground. It was a pleasure and relief to watch :-)
Friday, 24 March 2017
The Frames are finally here!!!!
The frames have finally arrived after it was delayed a week due to the rain. Eagerly waiting for Monday.......Frames scheduled to go up ...up. and ..up :-)
Thursday, 23 March 2017
Termite Physical Barrier.
Termite guard being installed. Our Slab is getting Red Fancy skirt ;-)