6th Day - Upper Floor started
Finally getting to look up in the sky and seeing frames up there toooooo ;-)......... Upper floor started today.
Monday, 10 April 2017
5th Day - Crane Power
A Long Reach Crane arrived on site to place steel beams and move the upper floor frames. Framing continued for the rest of the day.